By trusting the CIRIA 108 calculation, they saved over £2 million in formwork costs and completed the walls safely and on schedule. Nearly 40 years after its publication, CIRIA Report 108 "Concrete Pressure on Formwork" remains the gold standard for rational formwork design. It shifted the industry from fearful over-design to intelligent, risk-aware engineering.

Research (including later CIRIA updates) shows that for SCC, the coefficient (1.2) is insufficient. SCC can maintain fluid-like behavior for longer, leading to near-hydrostatic pressures.

Consider "horizontal layering" (pouring in lifts of 1-2 meters with a 30-minute delay between lifts). This allows lower layers to set, drastically reducing pressure on the bottom tie-rods.